Minister of Public Works Bishop Juan Edghill explained that $1 billion of the allocation would cater for a range of projects, including the countrywide streetlighting programme, community beautification, footpaths, and the removal of derelict vehicles and other obstructions.

The ministry has procured 80,000 grid lights and 20,000 solar lights, with installations guided by the needs of communities both on and off the grid.
“We are at the point where we are going to be using up all of the remaining grid lights. And still there will be gaps because we do the assessment village by village, NDC by NDC, and ensure citizens’ security,” Minister Edghill said.

In communities where narrow roads and existing utilities limit road construction, the funding will support concrete footpaths and the removal of derelict vehicles and construction waste.
Minister Edghill said the footpaths are being built so pedestrians, particularly children, senior citizens, and people using wheelchairs, can move more safely.
The additional funding will also allow the ministry to complete payments through the end of December 2026 for works under the miscellaneous roads and drainage programme, which is approximately 90 per cent complete. Some $4.6 billion was approved for that purpose.
The allocation further includes $7.5 billion for hinterland roads in Regions One, Seven, Eight, Nine, and 10, including $4.6 billion for Region Nine and $1.4 billion for Region One.
On the Moruca-Kwebanna road, an additional kilometre of concrete road is being constructed towards the hospital, while a separate maintenance contract will keep the existing roadway accessible during construction.
“The sum that is allocated for the one kilometre of concrete road, which is moving in the direction of Kwebanna…is $200 million,” he explained.
The money will also facilitate an additional 30 kilometres of the Linden-Mabura Road beyond Mabura Hill. Over $4 billion was approved by the committee to advance this project.
“We’ve been able to engage the contractor at the same 2021 rate to push another 30 kilometres. So, we’re now moving from Mabura Hill, 30 kilometres forward, and heading to the Kurupukari Bridge,” he said.

The first 121 kilometres of the road are 89 per cent complete and are expected to be finished by December 8, 2026.
Minister Edghill said contractual provisions, including liquidated damages, would be invoked if the contractor fails to meet the deadline.
Meanwhile, the East Bank corridor project leading to the Cheddi Jagan International Airport (CJIA) is 70 per cent complete, with a scheduled completion date of March 2027. More than $9 billion was approved to advance the works, as the ministry collaborates with contractors to accelerate progress and substantially complete the project before the end of 2026.
The committee also approved $3.5 billion for sea and river defence works. (Department of Public Information)